God is in the details – SOV

god-is-in-detailsSo how do you objectively evaluate and approve a progress claim that is accompanied with a schedule of values that contains broad categories such as concrete, windows and doors, or my favourite general requirements.

How do you know doors and windows are 50% complete? If there is only one dollar value for all doors and windows in the project, you don’t know how much the doors are versus the windows versus the hardware.  (Hopefully the hardware doesn’t cost as much as the door.) Or even the difference between the exterior doors or interior doors. These questions are a must, that you really need to ask the contractor right at the start before certifying any progress payments. Read More…